In GN4-2 JRA3 is responsible for further development of eduroam service. The roadmap was discussed during the Project Management Convention, resulting in the following:
...
- finalize first prototype for the service - Dec 2016
- launch pilot for the service - Jan 2017
- stop the pilot - May 2017
- eaas beta version - June 2017
- eaas v1.0, documentation and acceptanace testing - July 2017
- service launch and handover to production- Oct 2017
...
- analyse requirements - Dec 2016
- start development - Jan 2017
- finalize prototype - June 2017
- early adopters release and acceptance testing- July 2017
- service launch - Oct 2017
...