Support, operations and devops effort spent and planned Ask Ann to provide numbers from the SA5 budget.
...
Caution: Reporting on spent manpower in GEANT projects is not conceptualised for easy and accurate tracking of spent manpower for different services and for different aspects of work on those services (ie what was spent on development, support or operations). For GN4-1, it comes down on how much individual person claimed under certain task. eduroam development and operations were performed under same task in GN4-1 and therefore its impossible to make such differentiation at this point.
SA5 Task | Spent | Budget | Type of performed work |
T7 - eduroam | 310.850,83 € | 335.333,74 € | eduroam development and operations |
Proposal for additional KPIs related to usage, uptake and costs
...