Short name | Operational KPIs | Baseline 30/04/15 | Target 30/04/16 | Measured 30/04/16 | Explanation |
---|---|---|---|---|---|
KPI 1 | International eduroam authentications per month | 31,832,243 | 26,000,000 | 47,339,724 | Counts sucessful authentication requests that pases ETLR servers, for which time interval are those numbers - what is the start point |
KPI 1 | National eduroam authentications per month | 147,726,234 | 117,000,000 | 215,597,792 | Counts successful authentication requests that pases (only) FTLR servers for which time interval are those numbers - what is the start point |
[1] The target figure for end GN4-1 was set a number of months before the project began and is therefore lower than the baseline. The actual achieved growth exceeds that which would have been predicted with the same methodology of the original predictions.
Uptake trends
*NRENs and end-users where applicable
...
Proposal for additional KPIs related to usage, uptake and costs
...
Ann, Miro ? please add
Although GN4-2 Technical Annex does not have details on target values for KPIs, we have projected the target based on the current rate of usage growth and expected changes in the market. It is expected that growth of eduroam will be slower than in previous years due to full coverage/use in many organisations, and the potential impact of the abolition of roaming data charges in the EU. Nonetheless, as eduroam delivers more value than simply cost of network access, growth is still expected.
Short name | Operational KPIs | Baseline 30/04/16 | Target | Target M32 of GN4-2 | Explanation | |
---|---|---|---|---|---|---|
KPI 1 | International eduroam authentications per month | 47,339,724 | 43,000,000 | 49,000,000 | 55,000,000 | Counts sucessful authentication requests that pases ETLR servers for which time interval are those numbers - what is the start point |
KPI 1 | National eduroam authentications per month | 215,597,792 | 180,000,000 | 207,000,000 | 228,000,000 | Counts successful authentication requests that pases (only) FTLR servers for which time interval are those numbers - what is the start point |
[1] The target figure for end GN4-1 was set a number of months before the project began and is therefore lower than the baseline. The actual achieved growth exceeds that which would have been predicted with the same methodology of the original predictions.