Planning
Date (week) | Done? | SA5 Internal Goals | PLM Deliverable | Who |
25/05/2015 | Migrate pilot infrastructure from GN3plus | |||
01/06/2015 | Software migration to development process | |||
08/06/2015 | Confirm VMs for pilot | |||
29/06/2015 | Wrapup "InAcademia Data protection considerations and eduGAIN Code of Conduct compliance" Wrapup "InAcademia license and transaction fee considerations" | |||
20/07/2015 | Cost Benefit Analysis complete | |||
27/07/2015 | Service specification complete, specifically Specification towards SPs | |||
24/08/2015 | Define pilot use cases + key stakeholders | |||
31/08/2015 | Define pilot metrics | |||
28/09/2015 | First security Audit inc. whitebox code audit | Cost Benefit Analysis v1 Approval | ||
26/10/2015 | Cost Benefit Analysis v1 Approval | |||
23/11/2015 | pre Pilot Commence (original plan - maybe better UAT inc. finance and 1-2 stakeholders and move official pilot date back?) | |||
21/12/2015 | Product Definition Complete | |||
28/12/2015 | Product Value Proposition Complete | |||
04/01/2016 | Pilot | |||
25/04/2016 | start dialog with SA4 for software test |
...