1.3Supporting Services for Campus Identity Providers    
1.3.1Design Phase M1-M6 Mario
 D9.1 Market Analysis for Supporting Services for Campus Identity ProvidersEC DelM8 Mario
 Include info on TIER    
 Create CBA or update FaaS CBA M6  
 CBA Approval M8  
 Technical Design M6-M12 Mario & Janusz
 Prototype M18-M20 Mario Janusz
1.3.2Pilot M20-M28 Mario
1.3.3Transition to Production M30 Mario

VCs

Schedule: every Tuesday 3-4 pm CEST?

Kickoff VC 21.06.2016

 

Current Status

 

Milestone/Deliverable

...