...
- eduroam as a service - eaas : - detailed roadmap
- Overall system design specified – DONE
- Implement first prototype – ONGOING
- finalize first prototype for the service - – Dec 2016 [COMMITED]
- launch pilot for the service - – Jan 2017 [COMMITED]
-> functional except credential revocation; preliminary UI; see “Pilot Features” - stop the pilot - – May 2017 [PLANNED]
- eaas beta version - – June 2017 [PLANNED]
-> fully functional, near-final UIs; see “Beta Features” - eaas v1.0 , – July 2017 [PLANNED]
- documentation and acceptanace acceptance testing - July 2017– Sep 2017 [POSSIBILITY]
- service launch and handover to production - – Oct 2017 [POSSIBILITY]
- eduroam user diagnostics
- analyse requirements - Dec 2016
- start development - Jan 2017
- finalize prototype - June 2017
- early adopters release and acceptance testing- July 2017
- service launch - Oct 2017
- radsec scalability
- CAT development
Service availability and incidents
...