This page contains information about roadmap for devops, but may include description to actual issues and developments. RESPONSIBLE: Content is defined and maintained by devops team. |
Action | Description | Priority (1-lowest, 5-highest) | Status | Due Date | Assigned to | Comment |
---|---|---|---|---|---|---|
NRO audit - first draft spec released | NRO audit is a new measure of evaluating the practices of The aim is to gain knowledge of how well The ones who are not following the mandatory requirements The ones who are not following the recommended requirements | IN PROGRESS | Jan 2017 | |||
NRO audit - final spec released | NOT STARTED | Mar 2017 | ||||
NRO audit - first audit run | NOT STARTED | May 2017 | ||||
NRO audit - audit report released | NOT STARTED | June 2017 | ||||
NRO audit - spec update released | NOT STARTED | Mar 2018 | ||||
NRO audit - second audit run | NOT STARTED | May 2018 | ||||
eduroam DB ver 2 - public draft spec released | FINISHED | June 2016 | ||||
eduroam DB ver 2 - final spec released | IN PROGRESS | Dec 2016 | ||||
eduroam DB ver 2 - SW released | NOT STARTED | Jan 2017 | ||||
eduroam DB ver 2 - uptake review | NOT STARTED | May 2017 | ||||
eduroam DB ver 2 - close ver 1.0 support | NOT STARTED | Jan 2018 |
Examples for status codes:
NOT STARTED
FINISHED
IN PROGRESS
CANCELED