This page contains information about roadmap for devops, but may include description to actual issues and developments. RESPONSIBLE: Content is defined and maintained by devops team. |
eduroam devops team is responsible for operating and managing operational side of eduroam. Devops roadmap notes any outstanding activities from the "business as usual". Business as usual implies:
- technical part: maintain and when needed adjust configurations and resolve user reported problems for:
- ETLR1, ETLR2
- monitor.eduroam.org portal, eduroam database, f-ticks, monitoring service and CAT
- organisational part
- provide content for www.eduroam.org + eduroam wiki
- organise eduroam SG meetings
- liaise with GeGC
- liaise with JRA3
- expert level support for user questions received
Action | Description | Priority (1-lowest, 5-highest) | Status | Due Date | Assigned to | Comment |
---|---|---|---|---|---|---|
NRO audit - first draft spec released | NRO audit is a new measure of evaluating the practices of The aim is to gain knowledge of how well The ones who are not following the mandatory requirements The ones who are not following the recommended requirements | IN PROGRESS | Jan 2017 | |||
NRO audit - final spec released | NOT STARTED | Mar 2017 | ||||
NRO audit - first audit run | NOT STARTED | May 2017 | ||||
NRO audit - audit report released | NOT STARTED | June 2017 | ||||
NRO audit - spec update released | NOT STARTED | Mar 2018 | ||||
NRO audit - second audit run | NOT STARTED | May 2018 | ||||
eduroam DB ver 2 - public draft spec released | eduroam DB ver 2 is revised version of database that holds information about NROs, IdPs, Service Locations etc. | FINISHED | June 2016 | |||
eduroam DB ver 2 - final spec released | IN PROGRESS | Dec 2016 | ||||
eduroam DB ver 2 - SW released | NOT STARTED | Jan 2017 | ||||
eduroam DB ver 2 - uptake review | NOT STARTED | May 2017 | ||||
eduroam DB ver 2 - close ver 1.0 support | NOT STARTED | Jan 2018 |
Examples for status codes:
NOT STARTED
FINISHED
IN PROGRESS
CANCELED