The 1st iteration of pS Best Practices Assessment (ps BPA) will concentrate on system/documentation review. This iteration will last till the end of GN4-1
The expected result of the 1 iteration
Preliminary recommendations for improvements in vulnerability management/release and deployment management based on the documentation/system analyze
the plan, resources required (human and infrastructure like VMs) and schedule for the 2nd iteration - automation of pS R&M procedures, testing of the improved release and management procedure etc. 2nd iteration will be proceeded in SGA-2
(internal for Geant) to determine the potential need for a long-term support of pS dev team in terms of code audit, pen testing etc.