Number

Milestone name

Related work package(s)

Due date (in month)

Means of verification

M6.1

Draft exploitation report

WP6

5

Internal draft exploitation plan

M6.2

Communications toolkit, including some initial visuals to support communication

WP6

5

Logo and communication guidelines

M7.1

List of project events, target users and timeline

WP7

6

Web page with a list of planned events

M7.2

Overview of relevant events to contribute to

WP7

6

Internal document

M8.1

Kick off meeting

WP8

5

Blog post

M8.2

Draft Consortium Agreement shared

WP8

2

Internal document