This page contains information about roadmap for devops, but may include description to actual issues and developments. RESPONSIBLE: Content is defined and maintained by devops team. |
eduroam devops team is responsible for operating and managing operational side of eduroam. Devops roadmap notes any outstanding activities from the "business as usual". Business as usual implies:
- technical part: maintain and when needed adjust configurations and resolve user reported problems for:
- ETLR1, ETLR2
- monitor.eduroam.org portal, eduroam database, f-ticks, monitoring service and CAT
- organisational part
- provide content for www.eduroam.org + eduroam wiki
- organise eduroam SG meetings
- liaise with GeGC
- liaise with JRA3
- expert level support for user questions received
Action | Description | Priority (1-lowest, 5-highest) | Status | Due Date | Assigned to | Comment |
---|---|---|---|---|---|---|
eduroam DB ver 2 - public draft spec released | eduroam DB ver 2 is revised version of database that | FINISHED | 2016.06 (June) | |||
eduroam DB ver 2 - final spec released | IN PROGRESS | 2016.12 (Dec) | ||||
NRO audit - first draft spec released | NRO audit is the process of evaluation of the NROs against the | IN PROGRESS | 2017.01 (Jan) | |||
eduroam DB ver 2 - SW released | IN PROGRESS | 2017.01 (Jan) | ||||
NRO audit - final spec released | NOT STARTED | 2017.03 (Mar) | ||||
eduroam DB ver 2 - uptake review | NOT STARTED | 2017.05 (May) | ||||
NRO audit - first audit run | NOT STARTED | 2017.05 (May) | ||||
NRO audit - audit report released | NOT STARTED | 2017.06 (June) | ||||
eduroam DB ver 2 - close ver 1.0 support | NOT STARTED | 2018.01 (Jan) | ||||
NRO audit - spec update released | NOT STARTED | 2018.03 (Mar) | ||||
NRO audit - second audit run | NOT STARTED | 2018.05 (May) |
Examples for status codes:
NOT STARTED
FINISHED
IN PROGRESS
CANCELED