This section describes the plan to move the greenhouse concept forward.
Aim of this project: define a model to sustain the software developed by the GEANT association as a whole (including its members and/or associated peers worldwide).
Activity Name | Description | Comment | Start Month | End Month | Status |
---|---|---|---|---|---|
1. Concept Definition | Explore approaches to sustain software produced in the context of a collaboration where no model is already in place.
| The idea of the Greenhouse has been discussed for a while. Most of the background work has been done and it is available on this wiki space. See: Differentiating the TERENA Greenhouse
| Oct 2013 | Nov 2014 | DONE |
2. Initiation | Gather requirements and the options to implement the greenhouse | ||||
2.1 Needs assessment | Document list of requirements for different products. Assigned to: Nicole | Informal conversation with some of the project is ongoing for some time. See: Output: Assess a select number of key products. | 12 Jan 2015 | 20 Jan 2015 | NOT STARTED |
2.2 Gather info on models to implement the greenhouse | Short list of possible approaches that matches the core requirements identified in 2.1. Assigned to: Alessandra
| Output: a matrix on the wiki with possible approaches. See also: | 2 Feb 2015 | 27 Feb 2015 | NOT STARTED |
2.3 Document to present the most suitable options | Prepare a document to present a short list of options and their risks/benefits. Assigned to: Licia | Output: short document with recommendations on the approach to implement | 23 Feb 2015 | 31 March 2015 | NOT STARTED |
3. Select most suitable model | Select the approach to implement. | 31 March 2015 | 14 April 2015 | NOT STARTED | |
4. Execution | Implement the selected model. Assigned to: TBD |
TNC could be a good opportunity to gather some feedback if a proof-of-concept were available. | 15 April 2015 | End Jun | NOT STARTED |